They promised hundreds of jobs.
The contract says twenty.

xAI's subsidiary MZX Tech, LLC is building a data center in Southaven under the codename “Project Synergy.” The City and DeSoto County signed an agreement abating two thirds of its property taxes for up to ten years. Everything on this site comes from documents the City itself released — not from rumour, and not from us.

The numbers, from the signed record

Each figure below is quoted from a document on this site. Click any source to read it.

20
Jobs required by contract
Ad Valorem Tax Agreement, Recital B · read it
67%
Of property taxes abated
§ 6 — fee is one third of taxes owed · read it
10 yrs
Maximum abatement term
§ 4 · read it
16.5M
Gallons of city water billed
City water bills, Nov 2025 – Apr 2026 · see the meter reads
$6.69M
Paid to the city & its police
Three agreements · see the sequence
12
Records published in full
Released by the City · document library

Documented, promised, and still unanswered

A promise is not a contract, and a contract is not a receipt. This site keeps the three apart on every page. Community fact sheets circulating in July listed the size and length of the tax break as secrets nobody outside the room knew. They are not secret. They are written in the agreement the City released, and they are reproduced below.

✓ Documented

In a signed record you can read here
  • 67% of ad valorem taxes abated — the fee is a stated one third of taxes otherwise payable
  • Up to ten assessment years
  • At least twenty new jobs — the only job number in the contract
  • Binds future City and County boards, not just the ones that signed
  • $6,690,900 paid or pledged to the City and its police department
  • 16.5 million gallons of city water billed to MZX Tech in 132 days

? Promised

Said in public; no signed paper compels it
  • “Hundreds of permanent jobs” — no figure appears in the agreement
  • $60 million a year to DeSoto County by 2028
  • $20 million a year to Southaven's general fund
  • A $12.8 million sound wall
  • New police, fire apparatus and roads — contingent on money arriving

● Unanswered

What the released records do not show
  • What the abatement is worth in dollars. No official has published the total
  • Whether any board vote was ever taken in public on each payment
  • Whether air permits exist for the turbines at the site
  • What the schools receive under the apportionment
  • Any clawback if the twenty jobs never appear
How to close the gaps

Every item in the third column is a public records request away. Mississippi gives a custodian seven working days to answer, and if they refuse, the Mississippi Ethics Commission hears the complaint for free and can order the records released. We will file it for you, or you can file it yourself →

What they said, and what they signed

Said in public
“Hundreds of permanent jobs”
No specific number was ever given.
In the signed agreement
“at least twenty (20) new jobs”
Ad Valorem Tax Agreement, Recital B. No penalty is stated if even twenty never arrive.
Said in public
A $20 billion investment
Announced January 2026.
In the signed agreement
“over $10 billion”
Recital B. The contract's threshold is half the announced figure.
Counted on the ground
About 145 jobs so far
The number community researchers can actually verify at the first building.
In the signed agreement
No penalty either way
No released document requires repayment if the job numbers never arrive.
Said in public
The terms are confidential
The size and length of the discount were described as unknown.
In the signed agreement
One third of taxes, ten years
§§ 4 and 6, in the copy the City released. Read the clauses →

Start here

📜

The Deal

The Ad Valorem Tax Agreement, clause by clause: how much is abated, for how long, who is bound, and what xAI actually committed to.

Read the agreement →
💰

The Payments

$3.46M for roads, $1.85M from the Musk Foundation, $1,380,900 to the police department — and the dates they land relative to the tax vote.

See the sequence →
💧

Water

16.5 million gallons billed to MZX Tech in 132 days, read straight off the City's own water bills, meter by meter.

See the meter reads →
📁

Documents

Every record the City has released, hosted in full, summarised in plain English, with the redaction log.

Open the library →

File a Records Request

We file it as the Foundation so your name stays off it, and we publish whatever comes back. Seven working days by law.

File a request →
🔒

Anonymous Tip

If you work for the City, the County, or on the site and something looks wrong, tell us. We do not log your address.

Send a tip →

Southaven is the first, not the last

ExposeMississippi covers the whole state. Southaven is where it starts — because Southaven residents did the work first. The Safe and Sound Coalition filed the records requests that produced every document on this site, and DeSoto County is where the largest of these deals landed. That earns the first slot.

Each city gets its own subdomain as it comes online, and Southaven's home is permanently southaven.exposemississippi.com — so nothing published today breaks when the next town is added. Until then the front door lands here.

Another Mississippi town, same playbook?

Abatement negotiated behind closed doors, promises with no signed paper behind them, records requests that go unanswered — if that is happening where you live, tell us. The method on this site travels: the statute, the seven-working-day clock and the free Ethics Commission appeal are the same in all 82 counties.

Get the next document when it lands

One email when a request comes back or a new record is published. Nothing else, ever.

The Move Weight Foundation is a 501(c)(3) nonprofit. We are not affiliated with the City of Southaven, DeSoto County, the State of Mississippi, xAI, or MZX Tech, LLC.